2025-01-21 |
Started the conversion to a composer project and using Amara framework
JP as www-data
committed
on 21 Jan
|
---|---|
2024-12-05 |
Completed and tested. However, still need to convert the main.php into a Linux service
John P on MM
committed
on 5 Dec
|
2024-12-04 |
Restructured, scheduler running, still more testing required
John P on MM
committed
on 4 Dec
|